MGT 640 Topic 6 Assignment GCU

MGT 640 Topic 6 Project Monitoring and Control Problems

Details:
As a project management professional, it is important for you to be able to review numbers and report on what they are saying. It is also important for you to be able to use software that helps you keep timelines and keep the project running on time and smoothly. This assignment will continue to help prepare you for your responsibilities.Respond to the Following ProblemsYou are a project manager on a project that uses earned value management. The project has the following budget and status:

Project Duration (months):

14

Current Reporting Period (month):

6

BAC:

$387,000

Cumulative PV:

$68,345

Cumulative AC:

$78,379

% of the project completed through the reporting period:

19%

Estimate to Complete:

$294,677

Based on this information, determine the following:

  1. Cumulative EV
  2. Schedule Variance (SV)
  3. Schedule Performance Index (SPI)
  4. Cost Variance (CV)
  5. Cost Performance Index (CPI)
  6. EAC (bottom-up)
  7. VAC (bottom-up)
  8. TCPI

Based on your calculations in Question 1 above, respond to the following:

  1. What is the status of project accomplishment performance through the current reporting period? Why?
  2. What is the status of project cost performance through the current reporting period? Why?
  3. Is the project projected to complete over or under-budget? Why?
  4. Interpret the TCPI metric.

Based on your calculations in Question 1 above, an inexperienced and arrogant project analyst from the project management office has computed an additional metric: Cost Schedule Index, which equals SPI * CPI. He wants you to report this metric to the customer, instead of SPI and CPI separately. What should you do and why?

The program manager doubts your numbers. In particular, he does not believe your EAC number and requests that you calculate two independent EACs. In particular, he wants the following IEACs calculated from rows two and four in Table 23-5 in Snyder, (2013).

  1. Compute IEAC1= ((BAC- EV)/CPI) + AC
  2. Compute IEAC2= ((BAC- EV)/(SPI*CPI)) + AC
  3. Interpret IEAC1
  4. Interpret IEAC2
  5. Based on items 1-4 above, what do you think the program manager will request from you regarding the bottom-up EAC?

You are having a hallway conversation with the same project analyst from Question 3, who is realizing that he may not know as much about earned value management as he thought when he joined the company. Still, he is convinced that the following statements below are correct. How would you respond to him based on each statement (i.e., formulate a specific response and supporting rationale for each statement below)?

  1. EAC becomes Cumulative AC at project completion.
  2. Cumulative EV can be greater than BAC at project completion.
  3. EAC can be smaller than BAC at project completion.
  4. ETC can be greater than 0 at project completion.

Ensure that your last name is in the file name and submit your completed Excel file by the end of this week.

You are not required to submit this assignment to Turnitin.

 

Course Tutor helps in providing the best essay writing service. If you need 100% original papers for MGT 640 Topic 6 Assignment GCU, then contact us through call or live chat.

MGT 640 Topic 6 Assignment GCU

Best HLT 490 Professional Capstone Project Full Course
MGT 640 Topic 6 Assignment GCU

ACCT 553 DeVryBIAM 500 DeVryCIS 500 STRCIS 558 STRENG 105 GCUFIN 390 DeVryFIN 504 GCUHCA 545 GCUHCA 699 GCUHLT 306 GCUHLT 362 GCUHLT 555 GCUHLT 610 GCUHLT 665 GCUHOSP 594 DeVryHRM 600 DeVryMAT 144 GCUMGMT 600MGT 599 STRMGT 655 GCUMKT 373 GCUPSY 362 GCUPSY 565 GCUPSY 575 GCUPSY 665 GCUSOC 102 GCUSOC 320 GCUSOC 372 GCUSOC 412 GCUNSG 6440 SUHIM 515 GCUNSG 4029 SUHIM 615 GCUNSG 3029 SUNSG 4055 SUNSG 6630 SUNSG 6005 SUCRMJ 310PSY 510 GCUCRMJ 300 DevryCRMJ 425SPD 200 GCU, HLT 490 GCU ,ECH 340 GCU ,           ECH 440 GCU , ECH 355 GCU ,ECH 350 GCU ,LDR 461 GCU ,ECH 425 GCU ,REL 212 STR ,SCI 115 STR ,CIS 505 STR ,JUS 652 GCUMGT 640 GCU

Reviews

There are no reviews yet.

Only logged in customers who have purchased this product may leave a review.

Add to cart